Symtech Global Pvt Ltd is based in Noida, India. We develop mechanical parking projects from layout through manufacture and installation, and select and supply security and access equipment. Our work brings the equipment, the building and the people operating it into the same plan.

02 · How we build

Built to an agreed design.

Fabrication partners supply the steel sections and cut and bent parts. We machine pins, rollers and chain anchors in-house, press bearings and assemble chains, then send the sub-assemblies to site for final assembly. Purchased hydraulics and controls are checked against the bill of materials.

Symtech machine shop with two vertical machining centres and an operator at a tool bench
Machine shop: vertical machining centres
Fibre laser cutting a square steel tube, sparks at the cut, operator at the control screen
Laser tube cutting
Lathe turning a steel shaft under coolant
Turning a shaft
Stacks of galvanised platform sections shrink-wrapped for dispatch in the warehouse, a worker packing boxes beside them
Galvanised platforms packed for dispatch
Fabrication bay with a CNC plasma table and a fibre laser cutting bed
Plasma and fibre laser beds

03 · Installation and handover

Checks you can witness.

Our stack parking installation procedure includes five checks witnessed by the customer, covering the anchors, frame alignment, hydraulics, electrical safety and load trial. Each is signed before the next stage starts.

  1. 01

    Check site readiness

    Check the foundation, available height and power, and confirm that the delivered parts match the bill of materials.

  2. 02

    Verify the anchors

    Set the anchors and carry out sample pull-out tests before erecting the frame. The customer witnesses this check.

  3. 03

    Assemble the frame and platforms

    Check and record the alignment of the posts, then fit the sliders and parking platforms.

  4. 04

    Connect and inspect

    Install the hydraulics and controls, then check pressure, earthing and electrical insulation before operating the system.

  5. 05

    Test and train

    Run no-load cycles and a full-load trial with calibrated weights. Handover includes operator training, a spares kit, as-built drawings and the signed checklist.

04 · Where we work

Based in Noida. Working across India.

Office

Symtech Global Pvt Ltd
D-135, II Floor, Sector 63
Noida 201301, Uttar Pradesh
India

Reach

Delhi-NCR is the home market: Delhi, Noida, Ghaziabad and Gurgaon. Installations in Symtech's gallery run from Punjab to Maharashtra and Jammu. An 11-car puzzle system is also in manufacture for a private residence in Stamford, Connecticut, with remote installation support in the project scope.

Projects

See what could work on your site.

Share your location, available space and parking or access needs. A plan or photo helps, but you can start with a question.

Symtech in numbers

See our projects
Parking systems installed
2,000+
Across residential, commercial and public sites.
Indian states
10
With Symtech installations.
People behind the work
~20
Engineering, production, installation and after-sales.
Projects across borders
India & US
US puzzle parking project in manufacture.